With special permission, the slope for a 6-inch building sewer may range from 1/4 inch per foot to 1/8 inch per foot. Which expression best describes this range?

Prepare for the California Pipeline (C-34 License) Exam with expert-level multiple-choice questions, detailed explanations, and hints. Boost your confidence to ace the exam!

Multiple Choice

With special permission, the slope for a 6-inch building sewer may range from 1/4 inch per foot to 1/8 inch per foot. Which expression best describes this range?

Explanation:
The range is described by its endpoints in a specific order: it can vary from 1/4 inch per foot down to 1/8 inch per foot. Writing the range as “1/4 inch to 1/8 inch per foot” keeps that start-to-end direction exactly as stated. It communicates the same bounds, just in the same sequence. Reversing the order would convey the numerical spread but not reflect the way the range is presented in the question.

The range is described by its endpoints in a specific order: it can vary from 1/4 inch per foot down to 1/8 inch per foot. Writing the range as “1/4 inch to 1/8 inch per foot” keeps that start-to-end direction exactly as stated. It communicates the same bounds, just in the same sequence. Reversing the order would convey the numerical spread but not reflect the way the range is presented in the question.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy